WAF teams completes required connection as anchoring works begin

WAF teams completes required connection as anchoring works begin
Photo:WAF

Progress to the planned water works for the connection of Viria Water Supply to the Waila Water Treatment Plant system has progressed as per the plan.

WAF Chief Operating Officer Seru Soderberg says connection and assembling works, which involved cutting and welding began early this morning and that contractors with WAF teams have completed the required connection works at the site, with anchoring works to commence tonight.

Soderberg says the anchoring process will take some time for curing overnight, and with the rate of progress so far, they are planning to begin flushing works, bleeding works, refilling of reservoirs, as well as restoration from tomorrow morning.

He says they would like to thank their valued customers for their understanding and patience and for taking heed of the advisories of storing water for this weekend.

The WAF COO says water carting trucks continue to be on standby to assist when needed.

He says once again, they apologise for any inconvenience and thank their customers for their patience and understanding.

Stay tuned for the latest news on our radio stations

CFL radio frequencies
LIVE SCORES
Hurricanes vs Brumbies 7:05PM
Crusaders vs Blues 4:35PM
Chiefs vs Reds 7:05PM
Rabbitohs vs Sea Eagles 9:05PM
Knights vs Storm 8:00PM
Raiders vs Roosters 10:00PM
Fijiana vs Japan 10:04PM
Fiji vs Kenya 12:44AM
Fiji vs Great Britain 6:14AM
Maroons 20–22 Blues Full Time
Maroons vs Blues 10:05PM
Maroons vs Blues 10:05PM
Mexico vs South Africa 2:00pm
South Korea vs Czechia 2:00pm
Canada vs Bosnia and Herzegovina 7:00am
No recent scores