The road works on the Hibiscus Highway in the North is being done in two phases.
Fiji Roads Authority Chief Executive Officer Neil Cook said the first phase will cover 10 kilometers of road-sealing from Nagigi to Naqere.
Cook said this should be completed by the end of this year.
The second phase will cover 20 kilometers of road from Naqere to Kasavu.
This is scheduled to be completed by the end of next year.
Meanwhile $34 million is the allocation for the Buca Bay Road Project for this year.
Story by: Gwen Mc Goon