Road works not affected despite delayed shipment of bitumen - FRA

Road works not affected despite delayed shipment of bitumen - FRA
Acting CEO, Kamal Prasad

The Fiji Roads Authority says they have enough bitumen to last them 5 to 6 weeks despite there being a delay in the shipment.

Acting CEO, Kamal Prasad says they were supposed to receive the new shipment of bitumen by the end of last month but this has now been delayed to the 13th of this month.

Prasad says they have 140 metric tonnes of bitumen in the country which is sufficient for sealing 20 lane kilometres of road.

He says work is not being affected as it is raining around the country and taking the rainy weather into account, the bitumen should last them 5 to 6 weeks.

Stay tuned for the latest news on our radio stations

CFL radio frequencies
LIVE SCORES
Eels vs Rabbitohs 9:50PM
Titans vs Bulldogs 8:00PM
Broncos vs Roosters 10:00PM
Maroons 44–24 Blues Full Time
Maroons vs Blues 10:05PM
Argentina 2–0 Austria 5:00AM
France 3–0 Iraq Full Time
Norway 3–2 Senegal Full Time
NasinuFC 0–6 BaFC Full Time
NavuaFC 2–0 SuvaFC Full Time
LabasaFC 4–2 RewaFC Full Time
Drua vs Reds 4:05PM