Clearing works continue for the upgrading of the existing two lane roads to four lane roads from the Votualevu roundabout to the Wailoaloa road intersection in Nadi.
Nadi and Suva Roads Upgrade Project Program Manager Zaina Khan says Higgins Fiji started the clearing works last year.
Khan says they are continuing through Namaka with site clearance and utility services relocation work.
Higgins Fiji has been allocated $65.9M for this contract.
Meanwhile, the four lane widening road from Naisoso to the Votualevu roundabout is expected to be completed by the end of this month.