Queen Elizabeth Drive Upgrade Project to be completed by October

Queen Elizabeth Drive Upgrade Project to be completed by October

The Queen Elizabeth Drive Upgrade Project is expected to be completed by October this year.

Project Engineer, Adarsh Kumar says they have completed 50 percent of the work for Area 1, 70 percent for Area 2 and work continues for Area 3.

Area 1 is from Ratu Sukuna Road to Uwia Roundabout, Area 2 is from Uwia Road to Muanikau , while Area 3 is from Muanikau to Laucala Bay.

He says more than 100 people are employed under this project.

Meanwhile, Fiji Roads Authority CEO Kamal Prasad had earlier stated that the project will cost $66 million.

The project includes developing 4.5 kilometres of road with a new Nasese bridge, new traffic layout and roundabouts.

All underground utility services have also been upgraded under this project together with the construction of footpaths on both sides of the road for pedestrians, cycling lanes with upgraded streetlights and parking spaces.

China Railway 5 Group has been contracted for the project.

Stay tuned for the latest news on our radio stations

CFL radio frequencies
LIVE SCORES
Eels vs Panthers 9:50PM
Knights vs Roosters 8:00PM
Rabbitohs vs Storm 10:00PM
Spain 1–0 Argentina Full Time
Drua vs Waratahs 1:00PM
Ireland vs Argentina 8:10AM
Italy vs South Africa 11:40PM
Scotland vs New Zealand 2:10AM
U20 Northland vs U20 Ovalau 9:00AM
U20 Namosi vs U20 Coastland 10:50AM
U20 Macuata vs U20 Vatukoula 12:40PM
Yasawa vs Taveuni 9:00AM
Navosa vs Northland 10:50AM
Cakaudrove vs Tavua 12:40PM