The Public Rental Board will now have to get an extra $3 million to complete the new Raiwai flats.
Chief Executive Officer Mesake Senibulu said this is after the China Railway No.1 surpassed the $9 million budget allocated to them.
Senibulu said when they first met with the company, they decided that China Railway was to draw up the designs and start construction when the designs were approved.
However, Senibulu said it took them a couple of months before they had approved the designs as it did not follow the standard design which they had first agreed upon.
According to Senibulu, when they had agreed on the designs and approved construction to begin, China Railway No.1 did not provide them with a Bill of Quantities until half way through their works.
He said when they received the Bill of Quantities, the cost of the project had exceeded the $9 million budget which currently stands at $19 million.
Senibulu said after getting an opinion from a cost consultant, the PRB then decided that the project should now cost $12 million which they will try and get from the $20 million loan given by Exim Bank of China for the new Raiwai and Raiwaqa flats.
He added the company did not follow the building code of Fiji and structural requirements which they are still trying to sort out.
Construction is still on hold.