News

PRB will have to get extra funds to complete Raiwai flats

PRB will have to get extra funds to complete Raiwai flats
The Public Rental Board will now have to get an extra $3 million to complete the new Raiwai flats.

Chief Executive Officer Mesake Senibulu said this is after the China Railway No.1 surpassed the $9 million budget allocated to them.

Senibulu said when they first met with the company, they decided that China Railway was to draw up the designs and start construction when the designs were approved.

However, Senibulu said it took them a couple of months before they had approved the designs as it did not follow the standard design which they had first agreed upon.

According to Senibulu, when they had agreed on the designs and approved construction to begin, China Railway No.1 did not provide them with a Bill of Quantities until half way through their works.

He said when they received the Bill of Quantities, the cost of the project had exceeded the $9 million budget which currently stands at $19 million.

Stay tuned for the latest news on our radio stations

CFL radio frequencies
Scoreboard
8:00am
Nottm Forest vs Chelsea
3:00am
Man Utd vs Brentford
3:00am
Leeds vs Conventry
Full Time
Tailevu 14–18 Nadroga
Full Time
Fiji 21–23 Italy
Full Time
Fiji 24–19 Canada
Full Time
Fiji 31–14 New Zealand
Full Time
Fiji 19–28 Japan