The Fiji Electricity Authority is embarking on a major project which will take care of power supply in the Central division if there is a problem with the transmission line from Monasavu which happened last year.
Last year the whole of Central division faced power disruption for a number of days after the FEA’s transmission line went down after soil erosion.
FEA CEO Hasmukh Patel said they want to bring up the capacity of diesel power station by around 34 megawatts and this proposed project will cost FEA $50 million to $60 million.
Patel said they will be forwarding their proposal for Cabinet approval next week.
Meanwhile, FEA recorded an after tax profit of $75.3 million in 2012.
Story by: Dhanjay Deo