The road widening project from Caqiri road to Pilling road along the Kings highway has become one of the most challenging road works for the Fiji Roads Authority.
Nadi and Suva Road Upgrade Project Programme Manager Zaina Khan says they have identified that three major Water Authority of Fiji pipes that supply water to Valelevu and majority of Suva through Toorak and Flagstaff lie along the Kings Road section where they are widening the road.
Khan says the temporary protection method known as soil nailing will be used to provide reinforcement to the slope in which the Water Authority of Fiji pipes lie as heavy earthwork construction and excavation begins.
According to Khan, residents can expect no water cuts from the road works.
She says they always anticipated that there will be services in the road and they will have to work in close contact with the relevant stakeholders.
Khan also says they are still within budget.
Meanwhile, a record capital grant of $635.6 million was allocated to the Fiji Roads Authority for the development and upgrading of roads around the country for this year.
For next year, the Fiji Roads Authority has been allocated a record $635.7 million.
$79 million has been allocated for maintenance of roads around the country.