54% repair works complete at Ellington Wharf

54% repair works complete at Ellington Wharf
Source: Fiji Roads Authority

Repair works at the Ellington Wharf are progressing steadily, with the project now 54 percent complete.

The Fiji Roads Authority confirms that all essential piling works have been successfully completed, forming a strong foundation for the next stages of construction.

They say piling works are 100 percent complete, while the precast slab installation is currently at 70 percent.

The team is now focused on this critical phase, which plays a key role in shaping the new wharf structure.

FRA says one of the main challenges faced so far has been unfavourable site conditions for pile installation.

The remaining phases include backfilling works, construction of the concrete deck slab, and other ancillary works.

The final stage will see the installation and construction of the wharf deck, which will complete the repair project and restore full operational capacity.

Stay tuned for the latest news on our radio stations

CFL radio frequencies
LIVE SCORES
Crusaders vs Chiefs 7:05PM
Hurricanes vs Blues 7:05PM
Rabbitohs vs Broncos 9:50PM
Dolphins vs Roosters 10:00PM
Warriors vs sharks 5:30pm
Maroons 20–22 Blues Full Time
Maroons vs Blues 10:05PM
Maroons vs Blues 10:05PM
Mexico vs South Africa 7:00am
South Korea vs Czechia 2:00pm
Canada vs Bosnia and Herzegovina 7:00am
LautokaFC vs Nasinu FC 1:00pm
Ba FC vs NadrogaFC 3:00pm
LabasaFC vs SuvaFC 7:30pm