A total of 160 bridges and crossings have been damaged by Tropical Cyclone Winston costing $44 million.
Fiji Roads Authority Acting Chief Executive Officer Rory Garland said they have conducted their full assessment with 23 now being prioritized for more permanent structural restoration works.
Garland said most damage was caused by flood debris building up against structures which had caused both the structural damage and washout of approaches.
He said all other damaged crossings and bridges are open for use with some restrictions, however many of these will need permanent repairs to return them to their original level of service.
He added that it would take several years to complete permanent repairs and replacements for all TC Winston damaged bridges and crossings.